Calculate Your Dispute Timeline
Calculated Procedural Path
Dates assume each step is taken on its deadline. Steps marked “Indicative” reflect CAA's standard workflow rather than a deadline fixed by the Act. Dates do not allow for regional anniversary days (see the note below).
Notice of Adjudication Served (s 28)
Request CAA to Nominate Adjudicator (s 33(1)(d))
Notice of Willingness Issued (s 35(1))
Notice of Acceptance Served (s 35(2))
Serve Written Adjudication Claim (s 36)
Serve Written Response (s 37)
Claimant Reply (s 37A)
Optional Respondent Rejoinder (s 37A(4))
Adjudicator Determination (s 46)
Statutory Timeline Disclaimer
Working days: Saturdays, Sundays, national public holidays (Waitangi Day, Good Friday, Easter Monday, Anzac Day, the Sovereign's Birthday, Te Rā Aro ki a Matariki/Matariki Observance Day, and Labour Day), and the Christmas closure period (24 December to 5 January inclusive) are excluded from the calculation.
Regional anniversary days: the Act also excludes the day observed in the appropriate area as the anniversary of the province (s 5). This calculator does not exclude those days, because they differ from region to region. Where a regional anniversary day falls within a period, that deadline and each later step fall one working day later than shown. Which area is the appropriate area may depend on the circumstances of the adjudication.
This calculator is provided for informational purposes only. The parties should always refer to the Construction Contracts Act 2002, seek their own legal advice, and consult the adjudicator's specific directions when calculating or confirming final timeframes and deadlines under the Act.